Vertiv's PowerDirect 9000 and 5 MW PowerNexus solid-state transformer, announced November 17, 2026, extend 800 VDC power from single racks to AI pods and full data halls.

Vertiv Expands 800 VDC Portfolio for AI Compute Pods and Data Halls
Vertiv Expands 800 VDC Portfolio for AI Compute Pods and Data HallsTho-Ge / pixabay
By Marcus Bennett5 min read

Why it matters

  • Vertiv introduced the PowerDirect 9000 and PowerNexus MV SST on November 17, 2026, extending 800 VDC power to AI compute pods and data halls.
  • The PowerNexus is a 5 MW solid-state transformer converting medium-voltage AC to 800 VDC in a single stage, at up to 98% efficiency.
  • The PowerDirect 9000 power center is rated at 1.5 MW and scales in 60 kW increments via 27 hot-pluggable power-supply units.
  • The rack-level PowerDirect 5000, introduced May 2026, is rated up to 800 kW with at least 50 seconds of battery hold-up.
  • Vertiv is showcasing the portfolio at SC26 from November 17 to 22, 2026, with pilot programs underway.

Vertiv introduced the PowerDirect 9000 and the PowerNexus MV SST on November 17, 2026, extending 800-volt direct-current (800 VDC) power architecture from individual racks to AI compute pods and entire data halls. The move targets the steep power draw of AI compute, and it gives operators three distinct places to set the boundary where alternating current (AC) becomes direct current (DC).

The headline hardware is the PowerNexus, a 5 MW solid-state transformer that converts medium-voltage AC to 800 VDC in a single stage. The PowerDirect 9000, rated at 1.5 MW, consolidates pod-level conversion. Together with the existing rack-level PowerDirect 5000, introduced in May 2026, the portfolio now covers every scale of AI facility deployment.

Why does the conversion boundary matter?

Vertiv's core design principle is flexibility. Operators can now place AC-to-DC conversion at one of three points:

  • Beside an IT rack, using the PowerDirect 5000.
  • Ahead of a compute pod, using the new PowerDirect 9000.
  • At the data hall's medium-voltage connection, using the PowerNexus MV SST.

Vertiv expects AC and DC architectures to coexist, with no single adoption timetable across the industry. The accompanying architecture portfolio combines conversion, storage, distribution, protection, controls and monitoring, which allows 800 VDC to be introduced without committing an entire facility to one design.

The stakes are concrete. Moving conversion and storage outside the IT rack frees 8 to 16 rack units for compute, according to Vertiv — capacity that AI operators can fill with GPUs rather than power electronics. Each architecture also determines where backup, fault isolation and conversion losses are managed, so the choice extends well beyond voltage.

What does rack-level conversion offer?

The rack-level option remains the PowerDirect 5000, introduced in May 2026 for deployments that retain upstream AC infrastructure. The unit sits beside an IT rack and accepts 480 VAC, with 800 VDC or ±400 VDC output. Vertiv rates it at up to 800 kW, and its battery backup is designed for at least 50 seconds of hold-up time.

Using one power rack for one or two IT racks helps isolate faults and simplify maintenance, according to Vertiv. That isolation matters in dense AI halls, where a single electrical fault can otherwise knock out multiple compute racks.

Inside the compute rack, the 1U PowerDirect 3000 shelf converts 800 VDC down to 54 VDC for compute trays. The 90 kW unit delivers up to 98.5% peak efficiency and 180% pulse power for 0.5 milliseconds in Vertiv's specifications. The same shelf connects to the pod-level design, creating a common final conversion stage at the rack across architectures.

What is new at the pod level?

The PowerDirect 9000 consolidates conversion into one system positioned ahead of the racks. The power center converts 480 VAC to 800 VDC and is rated by Vertiv at 1.5 MW. It scales in 60 kW increments through 27 hot-pluggable power-supply units, letting operators match capacity to pod size.

Power distribution runs through the PowerBar Track DC busway, which carries power overhead to the shelves and provides a metered, breaker-protected drop at every rack. EnergyCore Li5 battery cabinets connect directly to the DC bus. Vertiv rates each cabinet at 200 kW of continuous backup and up to 98% conversion efficiency, with as many as six cabinets operating in parallel.

Consolidating conversion, backup and distribution removes the need for a power rack beside every IT rack and recovers row space, according to Vertiv. The design also supports mixed AC and DC loads, including colocation sites with different tenants, workloads and GPU generations — a practical constraint that pure-play AI cloud builders rarely face but that multi-tenant facilities confront daily.

How does direct medium-voltage conversion work?

At data-hall level, the PowerNexus MV SST sits in an outdoor, liquid-cooled container that Vertiv rates at up to 98% AC-to-DC efficiency. It eliminates two to three intermediate conversion steps found in conventional power trains, provides galvanic isolation (electrical separation) between input and output, and can support a 4.8 MW super-pod reference architecture without chaining multiple units.

Moving conversion outdoors can recover indoor space for compute, according to Vertiv. Fewer conversion stages also help reduce cumulative electrical losses, which compound at AI-scale power levels.

When paired with external energy storage through a DC/DC converter on the 800 VDC bus, the system can ride through electrical faults and smooth AI workload fluctuations, according to Vertiv. Bidirectional power flow can improve grid power quality and provide active power support. Battery communication ports coordinate storage with rapid load changes, a feature aimed at the erratic power profile of large GPU training and inference jobs. The containerized design also supports faster deployment and standardized replication across campuses.

What about DC safety and availability?

Safety features across the portfolio include:

  • Touch-proof busbars
  • High-voltage isolation
  • Midpoint grounding
  • Ground-fault detection
  • Arc-flash prevention

The accompanying service offerings are purpose-built for DC operating environments, rather than adapted from legacy AC procedures, according to Vertiv. That distinction matters for operators whose maintenance staff, tooling and training regimens were built around AC distribution.

What happens next?

Vertiv is showcasing the portfolio at SC26 from November 17 to 22, 2026. Pilot programs, technical validation and customer-specific collaborative development are already underway, according to the company.

For operators, the practical takeaway is granularity: retain AC infrastructure during a rack retrofit, consolidate power around a pod, or move medium-voltage conversion outdoors for a campus build. Vertiv's bet is that the AI data center market will not converge on one power architecture — and that the vendors who win will be those letting operators decide, rack by rack or hall by hall, where the current changes.

Source: unite.ai

Share this article:

More from Marcus Bennett

Marcus Bennett

Show full bio

Senior reporter covering companies, deals and strategy in artificial intelligence and machine learning at AI In Context.

718 articles

Related articles

  1. SolidUltra Raises €3 Million for Solid-State Transformers for AI Data Centers
  2. Jet Engines Pulled From Retired Aircraft Now Power AI Data Centers
  3. Nexalus and RENDA Launch Nova8, a Liquid-Cooled AI Server Built for Retrofit
  4. Voters Rejected Data Centers in 40 of 41 Ballot Measures
  5. Data Centre Power Market Set to Hit $107.06 Billion

« Previous articleNext article »