TeraWulf Falls 9% Despite Kentucky Power Deal Doubling Muskie Campus
TeraWulf fell 9% to $11.53 despite a Kentucky Power deal doubling its Muskie campus to 1,000 MW, as AI-linked data-center stocks slid ahead of NVIDIA earnings.

Why it matters
- TeraWulf fell 9% to $11.53 despite a Kentucky Power deal doubling contracted power at its Muskie campus in Grayson, Kentucky, to 1,000 MW.
- Applied Digital dropped 10% to $14.41 (down 41% YTD); Cipher Digital fell 7% to $6.38 (down 57% YTD).
- TeraWulf disclosed the amended agreements on November 6, 2026 alongside Q3 2026 results; the first 500 MW phase targets Q4 2028 and the second targets 2029, pending Kentucky PSC approval.
- Applied Digital reports 1.41 GW of leased critical IT load and $36 billion of contracted revenue; Cipher Digital's portfolio covers 700 MW and $16.6 billion.
- TeraWulf's HPC lease revenue is rising but adjusted EBITDA remains negative; contracted revenue includes the Justified Data lease with Anthropic and CB-4 rent at Lake Mariner beginning November–December.
By James Calloway
TeraWulf (NASDAQ:WULF) fell 9% to $11.53 in early trading, despite a Kentucky Power agreement that doubled contracted power at its proposed Muskie data campus to 1,000 megawatts. The sell-off swept the whole AI data-center landlord group: Applied Digital (NASDAQ:APLD) dropped 10% to $14.41, and Cipher Digital (NASDAQ:CIFR) fell 7% to $6.38. The NASDAQ 100 declined 2% as investors pulled back from AI-linked stocks ahead of upcoming earnings from NVIDIA (NASDAQ:NVDA).
The decline puts a straightforward question in front of the market. A company can double its contracted power pipeline and still lose nearly a tenth of its value in a single session. That tension — between locked-in capacity and the cost of financing it — is now the central debate around every name in this sector.
TeraWulf's year-to-date record remains the strongest of the three peers, up 0.4% against losses of 41% for Applied Digital and 57% for Cipher Digital. Whether that relative strength survives a group-wide financing scare is the open question.
What did the Kentucky Power deal actually change?
On November 6, alongside its Q3 2026 results, TeraWulf disclosed amended agreements with Kentucky Power Company covering its Muskie Data Campus in Grayson, Kentucky. The amendments doubled contracted power at the site to 1,000 megawatts (MW).
The timeline is staged. The initial 500 MW phase is targeted to ramp in Q4 2028, and a second 500 MW phase is targeted for 2029. Approval from the Kentucky Public Service Commission (PSC), the state regulator, is still required for that schedule. The agreement covers grid upgrades, customer bill credits and up to 1 gigawatt (GW) of demand at Muskie.
CEO Paul Prager framed the deal in the results release: "Muskie gives us a contracted path to a gigawatt of power."
Power availability is the binding constraint on data-center growth in TeraWulf's view, which makes a secured Kentucky site the core of the bull case. But a contracted path is not the same as delivered power. The PSC has not yet approved the schedule, and the first phase sits two years out.
The takeaway: the deal doubles TeraWulf's power runway on paper, but the regulator's sign-off and a 2028 ramp still stand between the announcement and the megawatts.
What does the peer slide say about the group?
Applied Digital fell harder than TeraWulf on the day, closing the session down 10% at $14.41. The stock is down 41% year to date. That weakness sits alongside a large contracted backlog: the company reports 1.41 GW of leased critical information technology (IT) load across five campuses and $36 billion of contracted revenue over initial base terms.
Cipher Digital traded at $6.38, down 7%, and is down 57% year to date — the largest loss of the three. Its contracted portfolio covers 700 MW gross and $16.6 billion of contracted revenue.
The pattern cuts against the idea that TeraWulf is the group's defensive name. Cipher Digital, the weakest performer on a yearly basis, declined least on the day. Backlog size, in other words, did not protect anyone: Applied Digital carries the biggest contracted revenue figure of the three and fell the most.
The takeaway: a contracted revenue base in the tens of billions did not stop a double-digit single-day decline anywhere in this group.
How does TeraWulf's landlord model differ from its peers?
TeraWulf operates as a vertically integrated power and data-center developer that controls land, power and interconnection at its sites. Long-term, credit-backed leases to AI tenants generate most of its revenue, while its legacy crypto mining business keeps shrinking. Management's stated strategy is to add new contracted capacity each year, finance projects at the project level, and recycle capital.
Applied Digital is a pure-play AI factory developer concentrated in the Dakotas, with heavy exposure to hyperscaler leases — leases signed with the largest cloud and AI operators. Cipher Digital is further behind in its own shift away from crypto mining toward high-performance computing (HPC) leases, and its sites sit mostly in Texas on the Electric Reliability Council of Texas (ERCOT) grid, the state's independent power market.
That geography and transition timeline leave Cipher Digital with the most transition risk of the three, while TeraWulf's mix of New York and Kentucky campuses spreads its power exposure across two regions. Diversification is a hedge, not an exemption — both campuses still depend on the same financing markets now pressuring the group.
The takeaway: the three companies share one business model — build capacity, lease it to AI tenants — and diverge mainly on how far each has moved away from crypto mining.
Can TeraWulf's relative strength survive the AI selloff?
TeraWulf's latest results show its HPC lease revenue rising, yet its adjusted earnings before interest, taxes, depreciation and amortization (EBITDA) — a measure of operating cash generation — remain negative. Heavy financing needs and execution risk on new campuses are the central concerns for the bears.
Applied Digital and Cipher Digital face the same pressures. Both carry large debt loads and depend on construction timing and hyperscaler demand holding up.
The bullish case for TeraWulf rests on specifics. Its contracted revenue base includes the Justified Data lease with Anthropic, plus rent from the CB-4 building at the Lake Mariner campus in New York, with those rent payments expected to begin in November and December.
Two conditions frame what comes next. TeraWulf still needs the Kentucky PSC to approve the Muskie expansion, and it must hold its year-to-date edge through a group-wide selloff. Until the AI data-center financing debate settles, the pressure on these stocks — gigawatts of contracted power notwithstanding — is likely to continue.
The takeaway: contracted leases with named tenants are the strongest card TeraWulf holds, but negative EBITDA means the story still depends on capital markets staying open.
Source: 247wallst.com
More from James Calloway
Show full bio
News editor covering people, launches and day-to-day practice in artificial intelligence and machine learning at AI In Context.
722 articles
Related articles
- Applied Digital Jumps 8% as CoreWeave Results Revive AI Data Center Trade
- AI Data Center Stocks Crater as Capital and Politics Tighten
- Nasdaq-100 Headed for Worst November Since 2008 as AI Stocks Slide
- Nvidia Loses World's Most Valuable Company Crown to Apple at $5.2 Trillion
- AI Buildout Faces Rising Credit Stress and a Withdrawn IPO