Belgium halts Google datacentre build as prosecutors weigh charges

Belgium ordered Google to stop building a 3-hectare datacentre near Charleroi after its permit was revoked, and prosecutors are being asked to probe the 'illegal construction'. A Council of State ruling is due 7 January.

Belgian authorities order Google to halt datacentre construction over lack of permits
Belgian authorities order Google to halt datacentre construction over lack of permitsengrahmad2653 / pixabay
By Sophie Lindqvist4 min read

Why it matters

  • Wallonia ordered Google's roughly 300 workers to halt a datacentre build near Charleroi on a site where the permit was revoked in August 2024/2025 revisions.
  • A report alleging 'the illegal construction of a building covering 3 hectares' is being submitted to Belgian public prosecutors.
  • Google's revised plan sought 600 cubic metres of water per hour from the Sambre River; minister François Desquesnes revoked it over drought concerns.
  • The Council of State ruling on Google's appeal is expected on 7 January.
  • Finland opened a criminal environmental investigation into a planned Google datacentre in October.

Belgian authorities have ordered Google to stop construction of a large datacentre near Charleroi, and a report alleging illegal construction is now heading to public prosecutors. The building, roughly 3 hectares in size, is nearly complete even though Google's latest planning permission was revoked in August.

The order came after inspectors visited the site in Aiseau-Presles, about 15km west of Charleroi, and found the structural work essentially finished. "Inspectors visited the site and observed that the building was almost finished, with the structural work completed, even though the permit had been refused," Raphaël Stokis, a Wallonia regional official, told the public broadcaster RTBF.

Stokis said the roughly 300 workers on site received a verbal order to stop, and that the order was confirmed in writing to Google. The company responded with a statement saying it was "committed to maintaining an open and collaborative dialogue" with the regional authorities.

How did a legal datacentre become an illegal one?

The project started cleanly. In 2024, Google received a permit to build three smaller, air-cooled datacentres on a 50-hectare business park on the site of a former coalmine. Then the plans changed.

In 2025, Google applied to merge two of the planned buildings into one much larger facility and switch from air cooling to liquid cooling. The new design called for drawing 600 cubic metres of water an hour from the nearby Sambre River. Local authorities approved the amendments in April, but residents and protest groups appealed.

In August, Wallonia's infrastructure minister, François Desquesnes, revoked the modified permit, citing drought concerns. Google appealed to Belgium's Council of State. A ruling in that case is expected on 7 January.

Underneath the permit dispute sits a physical reality: the building kept going up. Greenpeace published drone footage earlier this week showing construction continuing despite the revoked permit. "The tech giant is continuing work, even though in August the latest version of its planning permission to build this datacentre was revoked," the environmental group said.

Greenpeace filed an emergency appeal with local planning authorities and framed the stakes in blunt terms. "The climate crisis will only intensify in our region," it said. "Against this backdrop, the construction of energy-guzzling behemoths cannot be allowed to go unnoticed."

What are the possible legal consequences?

The regional government is not treating this as a paperwork dispute. Nicolas Yernaux, a regional government spokesperson, told Agence France-Presse on Friday that a report was being submitted to public prosecutors alleging "a major offence: the illegal construction of a building covering 3 hectares".

That wording matters. A referral to prosecutors converts a planning argument into a potential criminal matter, with the alleged offence defined by the sheer scale of the unauthorised structure. The building occupies about 3 hectares, or 7.4 acres, of the 50-hectare business park, and it is one of three datacentres Google originally planned for the site.

The stop order, the prosecutor referral and the Greenpeace footage together put Google in an awkward position. The company must now argue its appeal before the Council of State while defending its conduct on the ground — conduct its own permit applications no longer cover.

The likely flashpoint is water. The switch to liquid cooling and the plan to draw 600 cubic metres an hour from the Sambre is what triggered the August revocation, and drought risk in the region is the reason the minister gave. Expect that number to sit at the centre of the 7 January hearing.

Why does this matter beyond Belgium?

The Aiseau-Presles case is part of a wider pattern: European regulators are testing how far AI-driven datacentre expansion can go before it collides with environmental law. Google is not the only company facing that friction, but it is now facing it on two fronts.

In October, Finland opened a criminal investigation into possible breaches of environmental laws at a planned Google datacentre in the rural north of the country. Work there has been halted until environmental impact assessments are completed.

Two criminal-adjacent proceedings in two European countries within two months signals something firmer than routine permitting friction. The AI boom has pushed large tech companies to build datacentre capacity fast, and local authorities — in Wallonia as in Finnish Lapland — are showing they will use stop orders, permit revocations and prosecutors to slow that build-out where environmental rules are at stake.

What happens next is on a calendar. The Council of State ruling on Google's appeal is due on 7 January, and the prosecutors' response to the Wallonia report will determine whether the illegal-construction allegation becomes formal charges. Until then, the near-finished building sits idle, and 300 workers stay off the site.

Original: rtbf.be

Share this article:

More from Sophie Lindqvist

Sophie Lindqvist

Show full bio

Staff writer covering regulation, policy and their impact on artificial intelligence and machine learning at AI In Context.

959 articles

Related articles

  1. Belgium orders Google to halt data center construction over missing permit
  2. Google acquires a pre-developed 1.8-GW Wyoming AI data-center site
  3. Google Takes Over Crusoe's Wyoming Site for $17 Billion Campus
  4. Google's $15bn AI project draws land seizure claims in Andhra Pradesh
  5. Thailand pauses 49 datacentre projects as AI buildout strains grids

« Previous article