Belgium orders Google to halt data center construction over missing permit
Wallonia ordered Google to stop building a 7.4-acre data center building over missing permits, after Greenpeace drone footage showed work continuing post-revocation. A January court hearing will decide the River Sambre cooling fight.

Why it matters
- Belgian authorities ordered Google on Friday to halt construction of a 3-hectare (7.4-acre) data center building at a former 50-hectare mining site.
- Regional officials refused Google's permit amendment to cool the facility with River Sambre water during the summer, citing severe drought since spring.
- A court hearing on Google's challenge to the refused water-cooling permit is scheduled for January.
- Greenpeace Belgium released drone footage this week showing construction continued after the planning permission was revoked in August.
- In October, Finnish authorities also halted work on two Google data center sites pending environmental impact assessments.
Belgian regional authorities ordered Google on Friday to stop construction of a data center in southern Belgium, citing what a regional official called "a major offense: the illegal construction of a building covering three hectares," or 7.4 acres.
Nicolas Yernaux, spokesman for the Wallonia regional authorities, delivered that assessment to AFP. Inspectors visited the site on Thursday and informed Google representatives of the stop-work order in person, the regional authority said.
The order halts work at a former mining site spanning roughly 50 hectares in total. The dispute now at the center of the case is not the size of the project but its cooling system — and whether Google had the legal right to keep building while the permitting fight played out.
What does the stop-work order cover?
The alleged offense involves a single building under construction at the former mining site: three hectares, or 7.4 acres, of floor coverage. The site as a whole covers about 50 hectares. Wallonia's inspectors visited Thursday after pressure from environmental campaigners, and the formal order followed Friday.
Yernaux's framing — "a major offense" — signals the regional government's position that the construction itself, not merely a paperwork delay, is at issue. The order suspends work rather than revoking the project outright, but it lands in the middle of litigation that has already run for months.
Google did not immediately respond to a request from AFP to comment on the order.
Why is the project in court?
The legal fight began when Google applied to amend the terms of its planning permission for the site. The amendment sought to allow a cooling system drawing water from the nearby River Sambre, Belgian media reported. The initial project had envisaged air cooling.
Regional officials refused the application over the summer. The refusal came as severe droughts since spring stoked local opposition to tapping the river. Google has challenged the refusal in court, and a hearing on the challenge is scheduled for January.
The sequence matters for the enforcement action announced Friday. According to the timeline laid out by the regional authority and by Greenpeace Belgium, the latest version of Google's planning permission was revoked in August. After that revocation, work continued on the site.
What did Greenpeace document?
Greenpeace Belgium released a report this week stating that drone footage showed construction still progressing at the site. The group's inspection trigger traces back to that documentation: inspectors visited Thursday, and the stop-work order followed the next day.
"The tech giant is currently continuing its work, even though in August the latest version of its planning permission to build this data center was revoked," Greenpeace Belgium said in its statement.
The environmental group tied the dispute to the region's water stress. "The climate crisis will only intensify in our region. Against this backdrop, the construction of energy-guzzling behemoths cannot be allowed to go unnoticed."
Both quotations frame the stakes Greenpeace is asserting: a major infrastructure build advancing without valid permission, in a region that has faced severe drought since spring, using a river that regional officials declined to authorize as a cooling source.
Why does one permit dispute matter for AI?
The Brussels-area legal row is the latest confronting Google in Europe as tech giants race to build the data centers needed to support the Artificial Intelligence boom. The AI buildout is colliding with European permitting regimes, water constraints, and environmental review requirements — and the Belgian case shows how those collisions produce concrete enforcement, not just rhetoric.
The River Sambre dispute illustrates the resource question directly. Google's original plan used air cooling. Its amendment sought river water instead. Officials refused, citing drought conditions that have persisted since spring. Google's court challenge in January will test whether a company can substitute a water-intensive cooling design after initial approval of a different one.
The Finnish precedent is the second data point. In October, Finnish authorities ordered work halted on two Google data center sites in that country until mandatory environmental impact assessments could be completed. Two European governments, within weeks of each other, have now used stop-work powers against the same company's AI infrastructure buildout.
The Belgium case adds a third dimension: enforcement triggered in part by civil-society monitoring. Greenpeace's drone footage led to the inspection that produced the order. Regulators in this instance acted after an NGO documented continuing work — a pattern that could shape how data center construction across Europe is scrutinized.
What happens in January?
A court hearing on Google's challenge to the refused water-cooling permit is scheduled for January. Until then, the stop-work order stands, and the construction site sits at a former mine in Wallonia with a three-hectare building only partially realized.
The January hearing will determine whether the River Sambre cooling system can proceed. That decision carries weight beyond one site: severe drought since spring has made water allocation a regional political question, and the Sambre refusal was the regional government's answer the first time it was asked. Google is asking a court to reverse it.
The broader context keeps tightening. Finland's October halt, Belgium's Friday order, and Greenpeace's ongoing surveillance of the site together signal that the pace of AI data center construction in Europe now runs directly into environmental permitting, water scarcity, and enforcement mechanisms that governments have shown they are willing to use.
Source: feed.koreatimes.co.kr
More from Rebecca Stone
Show full bio
Correspondent covering companies, deals and strategy in artificial intelligence and machine learning at AI In Context.
922 articles
Related articles
- OpenAI pauses training of latest models as rogue agent reports mount
- Thailand pauses 49 datacentre projects as AI buildout strains grids
- Google acquires a pre-developed 1.8-GW Wyoming AI data-center site
- Aachen court makes it two: German judges keep holding Google liable for AI answers
- Judge rules NAACP lawsuit over xAI's Memphis data center can proceed