Texas moratorium threat puts Korean AI suppliers on notice
Some 80% of U.S. data center capacity in development now sits in Democratic-led states, and Texas Governor-elect Gina Hinojosa has pledged a moratorium on approvals, threatening Korean chip, transformer, cable and battery suppliers.

Why it matters
- About 80% of U.S. data center capacity under construction or planning is in Democratic-governed states, up from 35% before the elections, per the Korea Center for International Finance.
- At least 75 U.S. data center projects were delayed or canceled in Q1, equal to all of 2025, per MSCI.
- Texas Governor-elect Gina Hinojosa, taking office in January, pledged a moratorium on all data center approvals.
- Hyosung Heavy Industries won 386.5 billion won ($290.1 million) in U.S. transformer contracts in September.
- Hyundai Research Institute expects U.S. AI investment to expand through 2027 but slow around 2028.
- LS Electric signed a 168.9 billion-won switchgear deal with deliveries starting next year.
About 80 percent of U.S. data center capacity under construction or in planning is located in states set to be governed by Democrats, up from 35 percent before the midterm elections, according to a report by the Korea Center for International Finance. That single shift in political geography is now the central risk variable for Korean suppliers across the AI infrastructure chain, from memory chipmakers to transformer, cable and battery manufacturers.
The math is blunt. Texas, Ohio, Georgia and Nevada, where Democrats won governorships, account for roughly 40 percent of planned U.S. data center additions, the KCIF found. At least 75 U.S. data center projects were delayed or canceled in the first quarter of this year, matching the total for all of 2025, according to the New York-based finance company MSCI.
The wave of Korean contracts exposed to any slowdown is large and recent. Hyosung Heavy Industries secured a combined 386.5 billion won ($290.1 million) in contracts in September to supply ultra-high-voltage transformers to two major U.S. technology companies for AI data centers. LS Electric signed a 168.9 billion-won deal last month to supply switchgear (high-voltage electrical distribution equipment) for a U.S. hyperscale data center project, with deliveries scheduled to begin next year. Gaon Cable, through its U.S. subsidiary LSCUS, holds a five-year bus duct supply agreement and projects cumulative supply volume exceeding 4 trillion won by 2030.
What changes in Texas?
Texas, one of the largest U.S. data center markets, has become the focal point of uncertainty. Democrat Gina Hinojosa defeated Republican incumbent Greg Abbott in the state's gubernatorial election and takes office in January. She has pledged to impose a moratorium on all data center approvals until the state legislature passes laws "to protect Texans, so that Texans have a seat at the table to decide if and how data centers come into our community."
The pledge builds on restrictions already in place. Abbott ordered a pause on environmental permits and grid connections for data center projects while the state assesses their impact on electricity and water supplies, a review that could prolong uncertainty for developers regardless of Hinojosa's next moves.
Pennsylvania has moved in the same direction. Democratic Governor Josh Shapiro signed an executive order in August requiring developers to secure local approval and meet stricter standards on energy costs, environmental protection and community engagement. The order also made data center projects ineligible for the state's fast-track permitting program.
The regulatory push reflects pressure from below. Local communities across the United States are challenging projects over rising electricity bills, water consumption and the cost of expanding power grids, adding friction to an industry already facing power shortages and lengthy grid connection queues.
How exposed are Korean chipmakers?
For Korean semiconductor makers, the stakes run through customer investment plans rather than direct regulation. Long-term supply agreements help secure component volumes, but rising memory prices are increasing the cost of AI computing equipment and could make further expansion less economical, according to the Hyundai Research Institute.
If data center operators respond by delaying or scaling back investment, demand for memory chips could weaken as customers adjust their purchases of AI computing equipment. The institute expects U.S. AI investment to continue expanding through 2027, but warns that existing plans could be delayed and new investment reduced around 2028 as financial, regulatory and infrastructure constraints mount.
"If data center construction is delayed, canceled or scaled back, exports by companies in related industries — semiconductors, transformers, cables, electrical equipment and facilities — will be affected to some extent," Kim Tae-hwang, an international trade professor at Myongji University, said.
"These are not just one or two facilities but hundreds of data centers planned for construction over the longer term, so the effects could also spill over into related industries, potentially dampening activity across those sectors," Kim said.
How big is the power equipment exposure?
The power equipment and cable segment has arguably the most direct exposure, because its recent order books were built almost entirely on the U.S. infrastructure boom. The contracts landed within the past two months. Hyosung Heavy Industries' 386.5 billion-won transformer awards came in September. LS Electric's 168.9 billion-won switchgear deal was signed last month.
Gaon Cable's projection of more than 4 trillion won in cumulative bus duct supply by 2030 rests on the assumption that its U.S. customer keeps building at the planned pace. LG Energy Solution and Samsung SDI, meanwhile, are expanding North American production capacity for energy storage system batteries through investments in multiple facilities across the region, betting on the same demand trajectory.
Will Democratic governors actually block construction?
Kim urged caution against assuming that campaign rhetoric will translate into policy. "It is one thing to criticize these projects as an opposition party, but governing is different," Kim said, noting that campaign positions could diverge from the practical considerations of office.
"These projects can create local jobs and stimulate regional economies, particularly when foreign capital is invested in them. That could make governors hesitant to take decisions that would undermine development," he said.
Kim added that Democratic leaders must weigh environmental and labor concerns against the strategic imperative of maintaining U.S. leadership in AI as competition with China intensifies. "The United States would find it difficult to simply accept falling behind China in the competition for technological supremacy, particularly as China's capabilities in AI and digital technologies are growing rapidly," he said.
Lee Kyung-yeon, an analyst at Daishin Securities, said regulations could delay investment but would have a limited effect on the semiconductor cycle and earnings as long as data center construction continues. The impact on chip suppliers would remain contained unless the regulatory measures trigger a broad halt in construction, she argued.
"The key question going forward is not how hardline Democrats will be, but how quickly data center operators can factor the costs of meeting individual states' community demands into their business plans. The pace of that adjustment will also affect Korea's AI value chain," Lee said.
That framing sets the timeline for Korean suppliers. The Hyundai Research Institute's inflection point around 2028, when financial, regulatory and infrastructure constraints could bite simultaneously, gives exporters a window to watch: whether the 75-project delay count from the first quarter accelerates, and whether Hyosung, LS Electric and Gaon Cable's delivery schedules starting next year hold.
Source: feed.koreatimes.co.kr
More from Marcus Bennett
Show full bio
Senior reporter covering companies, deals and strategy in artificial intelligence and machine learning at AI In Context.
745 articles
Related articles
- Data Center Backlash Goes Global as AI Buildout Hits Local Resistance
- Chinese data center builders chase the U.S. AI infrastructure boom
- U.S. Midterm Fears Send SK Hynix Shares Down 10.44%
- Data Center Backlash Becomes a Political Force After Midterms
- Korea’s chip boom faces risk from U.S. data center curbs